Service Areas:

 

 22 July 2009

Construction Kaiser has successfully completed the concreting of all GTG Pedestals in Calabar 

Construction Kaiser announces the completion of the last 3 of 5 GTG Pedestals in Calabar all in the month of July 2009.
 
The concrete pour of GTG 1, 4, and 5 were successfully done on July 3rd, 8th, and 21st respectively. While the concreting of GTG 1 and 5 was achieved in 17 hours and 14 hours respectively; GTG 4 casting was completed in 12hours thus becoming the fastest GTG Pedestal concrete pour done by Construction Kaiser Limited so far.
 
Each of these five (5) Gas Turbine/ Generator Pedestals comprises of 450 cubic meters of grade 40 concrete, and 52 metric tons of high yield steel reinforcement, on this project. The combined weight of the Gas Turbine / Generator to be carried by these Pedestals is about 424 metric tons, (Gas Turbine- 250tons and Generator – 174tons
 
For each of the Pedestals, concreting was done from the Odisa 10 concrete batching plant, placed by one of our Schwing concrete pumps with a 32 meter boom, a 50tons Crane (with a skip bucket) and four Mixer trucks.
 
The management hereby congratulates the team, who gave their all, to achieve this feat.

 April 11, 2009 Construction Kaiser Ltd. cast Gas Turbine and Generator (GTG) pedestal in Calabar

 
Construction Kaiser announces another successful single concrete pour of the GTG 2 pedestal in Calabar.
The casting which started at started 9:25am was completed at 12:30pm; it lasted for 27 straight hours. This casting is under the 580MW National Independent Power Plant Project (NIPP) in Calabar.
 
This pedestal is one of the 4 Gas Turbine / Generator pedestals comprising of 450 cubic meters of grade 40 concrete, and 52 metric tons of high yield steel reinforcement, to be cast on this project. The combined weight of the Gas Turbine & Generator to be carried by this pedestal is about 424 metric tons, (Gas Turbine - 250tons and Generator -17tons). 
 
 
Concreting from the Odisa 10 concrete batching plant started at 9:25am on 11 April 2009 and at 12:30pm on 12th April 2009 casting of GTG2 pedestal was completed. The concrete was placed by our Schwing concrete pump with a 32 meter boom, a 50tons Crane (with a skip bucket) and Three mixer trucks. 

Latest News and Events In Construction Kaiser

29 March 2009 - Construction Kaiser Ltd. cast the 1st Gas Turbine and Generator (GTG) pedestal in Sapele 
 
Construction Kaiser hereby announces the successful single continuous concrete pour of the GTG1 pedestal, which was concluded on the 29th of March, 2009. This is under the 450MW National Independent Power Plant Project (NIPP) in Sapele.
This pedestal is one of the 4 Gas Turbine / Generator pedestals comprising of 450 cubic meters of grade 40 concrete, and 52 metric tons of high yield steel reinforcement, to be cast on this project. The combined weight of the Gas Turbine & Generator to be carried by this pedestal is about 424 metric tons, (Gas Turbine - 250tons and Generator -174tons).  This pedestal is carried by 800 millimeter diameter bored piles numbering over 22, driven to 30 meters depth.
 
Concreting from the Odisa 2530 concrete batching plant started at 11:30 on March 28th, 2009 and at 12:35pm on 29th March 2009 casting of GTG1 pedestal was completed. The concrete was placed by our Schwing concrete pump with a 32 meter boom, and five mixer trucks.
 
 The concreting of the second pedestal is due in the coming month, subject to the inspection of General Electric (GE) - the equipment manufacturers, while the others would follow after the completion of the steel piling work currently being carried out by TREVI Foundations.
 
Even though this is not the biggest single pour to be carried out by CKL, it has been the most important, being that it had to be continuous, and cold joints are not allowed.
We hereby congratulate the team, who gave their all, to ensure that this task was completed.

 

   

 

 

 

 

 

 
Copyright © Construction Kaiser Ltd. 2010   Legal & Privacy :: Contacts
Design by: IN Naija IT Solutions Ltd.